1.11 release process (was: [PULL] -next branch for 1.11)
Peter Hutterer
peter.hutterer at who-t.net
Mon Feb 28 21:55:13 PST 2011
On Mon, Feb 28, 2011 at 09:14:26PM -0800, Keith Packard wrote:
> On Tue, 1 Mar 2011 13:34:54 +1000, Peter Hutterer <peter.hutterer at who-t.net> wrote:
>
> > A number of fixes I've had lingering in my next branch.
>
> I was about to send out a message offering to run the 1.11 release. I'm
> still having fun doing it.
>
> Concerning the release process, are things going OK? Are there things we
> should change? Shorter? Longer? More release candidates?
>
> Do we need more formal rules for merging code? The RandR 1.4 server code
> was merged before the protocol and library APIs had seen sufficient
> review, but we don't have a formal process for either of those
> modules. Anyone know how to help with that? -- We don't have an official
> protocol tree maintainer at this point, although Daniel Stone did
> volunteer to put together another proposal for merging those trees
> together, and if that happened, maybe we could convince him to run a
> couple of cycles as release manager.
>
> Aside from that, here's my thoughts on the 1.11 release schedule;
> suggestions for changes are welcome. I like to avoid major holidays and
> to align with OS releases where convenient.
>
> Merge window closes: 2011-05-27
> Non-critical bug deadline: 2011-07-29
> 1.11 Release: 2011-08-19
>
> (this is just mirroring the 1.10 schedule, adjusting so that these dates
> all line up on a Friday)
>
> That gives us three months to get new stuff merged; I hope to be
> finished with RandR 1.4 long before that...
There were a few times during the last cycle where patches didn't get merged
but for no apparent reason. A simple email to the list stating something
like "I'm unavailable for this week and won't be merging patches" would be
enough to know what's going on.
Cheers,
Peter
More information about the xorg-devel
mailing list