On Fri, 2004-07-09 at 10:54, Kevin E Martin wrote:
> On today's release wranglers call, the group discussed plans for having
> the next X.Org Foundation release by August 25th. The primary new
> features planned for this release are three new extensions: Damage,
> XFixes and Composite.
>
> Some of the open questions are:
>
> - What is the state of each of these extensions, and what additional
> work is needed to complete their integration into the CVS repository?
> - What other functionality should be integrated before the release?
> - Is the DRI support up-to-date or are there additional bug fixes that
> need to be applied to the tree?
> - What other patches/bug fixes are needed?
> - Other items and/or open questions?
AFAIK the damage/fixes bits are ready to go, but we'll want to test them
with Composite and all the damage/fixes-using programs that composite
allows. I've pushed "Doing Composite in xorg" up to the top of my TODO
list so I should have something soon.
We'll need to take a look at bugfixes to pull in from DRI/Mesa CVS. DRI
CVS has been destabilized somewhat by the TLS prep work that's happened,
but supposedly all the known issues (except for the sparc asm dispatch,
which can be just disabled) have been fixed. I'll look into what needs
to be brought in some time before release, but not in the next couple of
weeks. It would also be nice to get
http://freedesktop.org/bugzilla/show_bug.cgi?id=709 fixed as I'm
concerned about compatibility issues if it isn't.
--